Project Type
Period House Refurbishment
Duration
32 weeks
Project Value
£320,000
The Challenge
The Georgian house had undergone a series of insensitive 1980s alterations — a polyurethane-coated pine kitchen, suspended ceilings concealing original plaster, and cement render externally. Removing these required careful archaeological-style investigation to assess what original fabric remained below. Listed Building Consent was required from Camden for all alterations, including the removal of the 1980s insertions.
Our Solution
We appointed a conservation architect who undertook a full building survey documenting all original and later fabric before any work began. Listed Building Consent was obtained for the full scope including removal of the 1980s alterations and repair of the original fabric. Specialist lime plasterers restored the original plaster ceilings and cornices. External cement render was removed and the original lime render reinstated.
Results
- ✓Listed Building Consent from Camden — comprehensive scope approved
- ✓1980s cement render removed and lime render reinstated to all elevations
- ✓Original plaster ceilings and cornices restored by specialist conservators
- ✓Six heritage sash windows overhauled and fitted with slim-profile double glazing
- ✓Bespoke in-frame kitchen respecting Georgian room proportions
- ✓Five bathrooms in period-appropriate finishes with modern fittings concealed
- ✓Estimated post-refurbishment value: £2.8m on a £2.1m purchase
Key Features
- ✓Grade II listed — Camden Listed Building Consent
- ✓Lime render reinstatement to all external elevations
- ✓Original plaster ceilings and cornices professionally conserved
- ✓Heritage sash windows with slim-profile secondary glazing
- ✓In-frame kitchen — Shaker, painted, with Calacatta marble
- ✓Five period-appropriate bathrooms with concealed modern plumbing
Specification
| Item | Specification |
|---|---|
| External render | St Astier NHL 3.5 lime render, gauged with Lafarge white cement 4:1, colourwashed |
| Plaster conservation | Lime putty consolidation, careful patching with matching coarse stuff |
| Sash windows | Original frames repaired; Slimlite slim-profile double glazed units, 4mm gap |
| Kitchen | Handpainted in-frame oak-framed kitchen, Calacatta Gold marble, Miele integrated appliances |
| Bathrooms | Burlington period sanitaryware, Perrin & Rowe taps, encaustic and Minton-style floor tiles |
| Boiler | Worcester Bosch Greenstar 8000 System, new pressurised cylinder, new radiators throughout |