Project Type
Single-Storey Rear Extension
Duration
11 weeks
Project Value
£72,000
The Challenge
The rear of the Victorian terrace was in a mixed-use street with both residential and light commercial neighbours. One neighbour operated a small business that received deliveries, and site access for materials and skips required careful management to avoid conflict. The proposed extension depth also triggered a Party Wall notice with the property to the rear, which initially raised concerns about the impact on their light.
Our Solution
A carefully planned site logistics schedule was produced before works began, coordinating deliveries and skip placements with the neighbouring business's schedule. The party wall surveyor produced a right-to-light assessment that confirmed the extension would not materially affect the rear neighbour's daylight. The award was agreed in 3 weeks. Camden approved the planning application in 7 weeks.
Results
- ✓Camden planning approval in 7 weeks
- ✓Party wall award agreed in 3 weeks — right-to-light concern resolved
- ✓Site logistics coordinated with neighbouring business throughout
- ✓20m² open-plan kitchen-diner created
- ✓Three-panel bifold doors to courtyard garden
- ✓Structural rooflight — 1800×900mm over kitchen
- ✓Estimated property value uplift: £80,000
Key Features
- ✓Camden planning consent
- ✓Right-to-light assessment — party wall award agreed
- ✓Site logistics management in constrained mixed-use street
- ✓Three-panel bifold doors to rear garden
- ✓Structural rooflight flooding kitchen with natural light
- ✓Underfloor heating throughout extension footprint
Specification
| Item | Specification |
|---|---|
| Extension walls | Brick-and-block cavity construction, 100mm Rockwool cavity fill, London stock brick exterior |
| Bifold doors | Smart Aluminium three-panel bifold, 2700mm wide, RAL 9005, low-threshold, double-glazed |
| Rooflight | Glazing Vision Flushglaze, 1800×900mm, triple-glazed, aluminium-framed |
| Kitchen | Bespoke painted Shaker kitchen, Silestone Blanco Nieve worktops, Neff integrated appliances |
| UFH | Warmup Clypso wet underfloor system, 75mm screed, extension footprint |
| Flat roof | Alumasc Hydrotech hot-melt waterproofing, inverted insulation, 20-year guarantee |